Having only 9 large air tankers on full time exclusive use contracts is a major reduction from the 44 we had in 2002, but after September 4, 2012 there may be only 6 working, unless the U.S. Forest Service extends them beyond the mandatory availability period specified in their contracts. The above chart, which we prepared using data supplied by the National Interagency Fire Center, shows the mandatory availability period for the 11 air tankers that we started with at the beginning of the 2012 fire season. We lost two on June 3 when one crashed, killing the two person crew, and a second that was damaged after the landing gear failed to fully extend upon landing.
Knowing at the beginning of the fire season that only 11 air tankers would be available, the USFS still only scheduled each air tanker on a staggered basis for five to six months each, rather than extending the beginning and ending times for each of these limited resources. In a normal wildfire year with normal weather, the fire season in the northern latitudes begins to decline in September. We no longer have “normal”, and even if we did, having only 6 air tankers after September 4 makes it impossible to initial attack new fires with both air and ground resources, increasing the chance that some fires will become large, destructive, and very, very expensive to suppress. Some may even cause fatalities and destroy hundreds of homes as we have seen too often this year already.
As a minimum, during the short term, the availability periods for all nine air tankers that are left on long term contracts should be extended until November 30, IF the vendors can supply crews to maintain and fly the aircraft during those time frames. And the three very large air tankers, the two DC-10s and the 747, should be brought on and awarded long term exclusive use contracts.
In addition, instead of shutting down every air tanker for one day a week while the flight crew takes a well-deserved day off, bring in a relief crew to fly the aircraft for one or even two days. And even use relief crews to give the pilots a week off once or twice a summer, reducing the hardship on them and their families. This could improve the turnover rate of flight crews who are typically away from home for much of the year.
Before the end of this year, Neptune expects to bring on two additional BAe-146 air tankers, and Minden has plans to deploy one BAe-146. In 2013 there should be four more air tankers: an additional BAe-146 from Minden, two MD87s from Aero Air, and one RG85 from Aero Flite.
For the long term, the USFS should, instead of adding just 7 air tankers over the next two years, that number should be increased to 25 to 30 over the next 4 years, bringing the total number of air tankers to 35 to 40.

*Note about the chart: The ending date for Tanker 40 is unclear, since the contract list, as shown above, lists the date as October 43, 2012.