A third DC-10 air tanker to become available

Tanker 912, DC-10
T-912 after arrival at Albuquerque. Photo by 10 Tanker Air Carrier.

A third DC-10 air tanker is expected to become available in the very near future. 10 Tanker Air Carrier has announced that the conversion of their third Very Large Air Tanker is complete and they expect to receive it at their company headquarters this week in Albuquerque. The final step will be certification by the Forest Service, after which it will be dispatched where requested by fire managers. It will be designated as Tanker 912.

The DC-10s always carry 11,600 gallons of fire retardant unless a smaller load is requested by fire managers. That is three to six times more than conventional air tankers.

Updated: MD-87 and DC-10 back in the air

(Originally published at 11:24 a.m. MDT, August 3, 2014; revised August 4, 2014)

The issues that kept one of the DC-10s and all three of the MD-87 air tankers grounded for a while have been partially mitigated for the MD-87s, and totally fixed in the case of the DC-10.

DC-10

Tanker 910, a DC-10 operated by 10 Tanker Air Carrier, suffered some damage to a wing on July 19 as it was taxiing at the air tanker base at Moses Lake, Washington. While relocating in the loading pit area the aircraft struck a portable “air stair”, a structure that can be pushed up to the aircraft door. Two people on the ground were marshaling the DC-10 as it slowly moved, directing it where to go and supposedly watching for obstructions. Rick Hatton, President of 10 Tanker, told us that the air tanker was back in service on July 28.

Mr. Hatton said their second DC-10, Tanker 911, has been busy on fires. The third one being built now, Tanker 912, was test flown on August 2. It will enter service later this month, perhaps as early as August 11.

MD-87s

On June 27 Erickson Aero Tanker recalled the three MD-87s they were operating, tanker numbers 101, 103, and 105, “due to intermittent engine surges when dropping [retardant at] high coverage levels”, according to the U.S. Forest Service. The Oregonian later reported that retardant was being ingested into the engines. On June 30 Tanker 101 returned to service, but with restrictions. Tanker 105 should be in service the week of August 4, but with same restrictions.

We have confirmed that the air tanker is limited to no more than coverage level four, which is four gallons per 100 square feet — about half of the maximum coverage level for fully capable air tankers. Our understanding of the issue is that the MD-87s have two retardant openings on the belly. On most air tankers they are called “doors”, since they operate much like a door on a hinge, swinging down on some air tankers. But the MD-87 has two “spades”, which function like a stopper in a bathtub. The spade in the aircraft normally plugs the hole, but raises, in a constant-flow manner, to allow retardant to flow around it and exit the aircraft.

Tanker 101 is using just the left spade instead of both. That spade now has half a funnel at the leading edge to get the retardant moving backwards as it comes out. There is a report that a slight mist was still contacting the wing but it appears that retardant is no longer going into the engines. The leading edge slats make that small amount of retardant that touches the wing look worse than it is.

One of the MD-87 pilots is qualified for initial attack.

Phone calls to Erickson Aero Tanker requesting comments on this issue were not returned.

UPDATED: DC-10 damages wing while taxiing at Moses Lake

Wing damage on Tanker 910.
Wing damage on Tanker 910.

(UPDATED, July 25, 2014: excerpts from SAFECOMS are at the end of the article. UPDATED September 3, 2014: a lessons learned report can be found HERE.)

One of the DC-10 Very Large Air Tankers incurred some damage to a wing July 19, 2014 while it was taxiing at the air tanker base at Moses Lake, Washington. While relocating in the loading pit area Tanker 910 struck a portable “air stair”, a structure that can be pushed up to the aircraft door. Two people on the ground were marshaling the DC-10 as it slowly moved, directing it where to go and supposedly watching for obstructions.

air stair
The “air stair” that was struck by the wing.

The wing was damaged on the front and back sides –the aileron and the slats. Rick Hatton, the President of 10 Tanker Air Carrier, said on Sunday that parts to repair the damage were en route to Moses Lake. The company’s other DC-10, Tanker 911, was also at the tanker base when the accident happened.

Mr. Hatton said retardant systems tests on their third DC-10 which is being converted now into an air tanker will begin the week of July 28. In a month or two they hope to have it fully operational. It will be designated as Tanker 912.

Below is a copy of a portion of SAFECOM 14-0491 about the incident. Click on the image to see a larger version.

SAFECOM 14-0491

Below is a copy of a portion of SAFECOM 14-0446 about the incident. Click on the image to see a larger version.:

SAFECOM 14-0446

Number of air tankers increases for the first time since 2007

Conair RJ85 first flight
The first flight of Conair’s BAe Avro RJ85 in September, 2013, built for Aero-Flite. Conair photo by Jeff Bough.

The large air tanker fleet in the United States is on track to have more than double the number that were flying at the beginning of the summer in 2013. Last year there were nine large air tankers available near the beginning of the western fire season, and by mid-July this year there are expected to be 20 on contract that are fully certified, flyable, and ready to assist firefighters on the ground. Air tanker UTF In 2002 there were 44 large air tankers on exclusive use contracts, but that number as been generally in a downward spiral since then until it reached the low point of nine in 2013. Thanks to the the U.S. Forest Service adding three additional jet-powered BAe-146s to the “legacy contract” temporarily this year, and with nine other air tankers being on five-year or temporary one-year “next generation” contracts, we expect the air tanker fleet to be the largest since 2009.

Large air tankers-2014

Five of the 20 air tankers are on temporary one-year contracts added under the “additional equipment” provisions of the contracts that Neptune and 10 Tanker Air Carrier have for their BAe-146s and DC-10s. Unless the USFS decides again next year to award them another one-year contract (if they have the funds to do so) those five may disappear and the total number could decrease to 15.

Within the next week or so 16 large air tankers should be fully activated and on duty. There are still four that have contracts but are still going through the final stages of conversion, live drop tests, or approval of a Supplemental Type Certificate (STC) by the Federal Aviation Administration.

In addition to the 20 large air tankers, there will be 33 single engine air tankers (SEATs) on exclusive use national contracts.

10 Tanker Air Carrier is converting their third DC-10. It has all of the necessary approvals and is expected to be ready to fight fire in July.

Aero-Flite has the approval of the Interagency AirTanker Board and is waiting on the STC before their two RJ85s can begin work. They hope to have everything all squared away by mid- to late June.

Minden has been working on their BAe-146 for several years and has scheduled their airborne drop tests, the “grid test”, to begin the week of June 16. They are waiting for the FAA to issue their STC. The FAA representative who was working on it had to leave the country on an assignment, slowing down the process.

By mid-summer there will be three additional air tankers that that the U.S. Forest service could activate on one-year additional equipment contracts. Neptune, Erickson Aero Tanker, and Aero-Flite will each have one additional approved air tanker sitting on their ramps.

The U.S. Forest Service could have, with the stroke of a pen, a total of 23 large air tankers flying this summer. The states in the far west are expected to have an above normal wildfire potential this summer. If that turns out to be accurate and houses are burning and residents are being killed, some questions will be asked if those three recently converted next generation air tankers are still cooling their wheels on an airport ramp because a bureaucrat in the Department of Agriculture decided to look the other way.

Tanker 41
Tanker 41, a BAe-146, flyover May 21, 2014 at the University of Montana during the Large Fire Conference at Missoula. Photo by Bill Gabbert.

A second DC-10 now on contract

Tanker 910, a DC-10,
Tanker 910, a DC-10, at Rapid City, April 23, 2013. Photo by Bill Gabbert.

The U.S. Forest Service has added a second DC-10 on the exclusive use “next-gen” air tanker contract. Rick Hatton, the President and CEO of 10 Tanker Air Carrier, told Fire Aviation that their second DC-10 very large air tanker, Tanker 911, has been added to the exclusive use fleet. It had been on a call when needed contract, and would only be activated occasionally, and only if it was available.

Mr. Hatton said their third DC-10 which is being converted now, Tanker 912, should be airborne “by mid-season”, and it is also is being added to the exclusive use contract. So by sometime this summer, there will be three DC-10s available to fight fire.

10 Tanker owns three other DC-10s that are awaiting modification, Mr. Hatton said.

GAO releases details of air tanker contract protest decision

GAOThe General Accountability Office has released their 23-page decision documenting why the agency sustained the protest filed by three companies over the sole source air tanker contract that the U.S. Forest Service awarded to Neptune Aviation December 12, 2013. The non-competitive contract, worth $141 million to $496 million, specified that Neptune would supply two or more next-generation air tankers, BAe-146s, for the next four to nine years beginning in 2014.

In our previous article about the decision we included the text of a press release issued by the GAO, but this 23-page document provides much more detail.

GAO sustains protest of air tanker contract

Neptune's Ait Tanker 41
Neptune’s Tanker 41, a BAe-146, at Missoula, August 11, 2012. Photo by Bill Gabbert.

(Originally published at 3:15 p.m. MT, March 31, 2014; updated at 8:40 a.m. MT April 1, 2014 with the text of a statement released by the GAO, and again at 11:20 a.m. MT April 1, 2014 with a response from the USFS.)

The Government Accountability Office announced today that they sustained the protest filed by three companies over the sole source air tanker contract that the U.S. Forest Service awarded to Neptune Aviation December 12, 2013. The non-competitive contract, worth about $141 million, specified that Neptune would supply two or more next-generation air tankers, BAe-146s, for the next four to nine years beginning in 2014.

A spokesperson for the GAO said their review concluded that the U.S. Forest Service “could not reasonably justify” the non-competitive process used in awarding the contract to Neptune.

The three companies that protested the sole source contract were Coulson Aviation (USA), Inc; 10 Tanker Air Carrier, LLC; and Minden Air Corp. If only the minimum two air tankers were signed up, the value of the contract would be about $141 million. If the options for five additional tankers were utilized, it would be hundreds of millions.

The protest automatically halted the activation of the sole source contract when it was filed in December.

We asked the USFS for their reaction to the GAO decision, and if other air tankers will be brought on, either by activating options under existing legacy or next-gen contracts, or will additional contracts be pursued? We received the following statement issued by their Washington office Tuesday morning:

The U.S. Forest Service is committed to ensuring that we have all of the resources we need to fight wildland fire and protect the lives and property of the American people. Airtankers are an important part of our efforts and we are currently reviewing the GAO recommendation.

In the protest filed with the GAO, hundreds of pages were submitted, listing dozens of reasons why the three companies felt the sole source contract should be terminated.

The Coulson company argued that on several occasions they told the USFS that they could supply more than the one C-130, but were told that the funding situation was too uncertain to commit more air tankers. Then a few months later, the USFS issued a contract potentially worth at least $141 million.

10 Tanker made similar offers, and in fact had a second DC-10 fully certified and on a call when needed contract that they would have liked to convert to an exclusive use next-gen contract. They also said they are working on retrofitting a third DC-10 which they expect to have ready to go by the end of calendar year 2014.

This was the third USFS air tanker contract that has been officially protested in the last two years. Two of those were sustained by the GAO, the recent sole source contract and the original attempt to issue contracts for next-gen air tankers, while the third, filed by Neptune, was dropped five months before the company received the sole source award in December.

Neptune will have six Korean War vintage P2Vs (2,082 gallons each) and one jet-powered BAe-146 (3,050 gallons) on exclusive use contract this year in what the U.S. Forest Service calls the “legacy” air tanker category. The company expects to have four additional BAe-146s ready to fight fire this year that are not currently on contract.

10 Tanker Air Carrier has one DC-10 Very Large Air Tanker on exclusive use contract and another on a call when needed contract. The company is in the process of retrofitting a third DC-10. They each carry 11,600 gallons of fire retardant.

Coulson has one 3,500-gallon C-130Q on exclusive use contract and hopes to acquire and convert a second C-130.

Minden has a contract for a BAe-146 but it has not yet been tested or approved by the Interagency AirTanker Board.

The complete text of a statement by the GAO about the decision is below. It was written March 31 and released April 1, 2014.

****

“The following is a statement from GAO regarding today’s decision resolving bid protests filed by Coulson Aviation (USA) Inc., 10 Tanker Air Carrier, LLC, and Minden Air Corp., B-409356.2 et al., March 31, 2014.

On March 31, the U.S. Government Accountability Office (GAO) sustained, or upheld, the protests filed by Coulson Aviation (USA) Inc., of Port Alberni, British Columbia, Canada, 10 Tanker Air Carrier, LLC, of Albuquerque, New Mexico, and Minden Air Corp., of Minden, Nevada, challenging the sole-source award of a contract by the Department of Agriculture (USDA), U.S. Forest Service, to Neptune Aviation Services, Inc., of Missoula, Montana, for airtanker services to support wildland firefighting.  The contract contemplates Neptune providing at least two modern large airtankers for up to 9 years (the contract also contains options to add up to five additional aircraft in each year).  The total estimated value, based on all possible aircraft over all years, is approximately $496 million.
Continue reading

A sole source air tanker award, how it developed

BAe-146 drops on Devore Fire
A Neptune BAe-146 drops on the Devore Fire, November 5, 2012. Photo by Rick McCLure.

Today, March 11, the Government Accountability Office will hold a hearing at their office in Washington, DC to consider the protests filed by three air tanker companies over the propriety of the U.S. Forest Service’s (USFS) noncompetitive contract award to Neptune Aviation Services, Inc., for next-generation large airtankers. The hearing was scheduled to begin at 9 a.m. ET, but was a closed session, open only to GAO personnel, attorneys for the three companies that protested the contract, and two individuals from the Department of Agriculture who have been asked to be available to testify, Lisa Wilusz, a Senior Procurement Executive, and Gregory Parham, the Chief Acquisition Officer. Even the owners of the protesting companies are prohibited from attending, to prevent them from being exposed to their competitors’ trade secrets.

Protesting the sole source award for two BAe-146 air tankers to Neptune, are Coulson Aviation (USA), Inc; 10 Tanker Air Carrier, LLC; and Minden Air Corp. If only the basic two air tankers are signed up, the value of the contract would be about $141 million. If the options for the five additional tankers are utilized, it would be hundreds of millions.

The GAO is required to make their decision about the propriety of the sole source award by March 28.

Fire Aviation has reviewed almost three dozen documents filed by the protesting companies as well as the USFS’ Motion to Dismiss the protests. The files contain letters of protests, supplementary protests, transcripts of Congressional hearings, “declarations” written by some of the principles, an NTSB report, and an article from FireAviation.com. While it remains to be seen which side the GAO will favor, regardless of the outcome it is clear that after the dust settles the attorneys will probably close shop for two weeks and take their families to Bora Bora.

Most of the documents have redactions, some more than others. One or two are virtually useless as a result, but most still contain a great deal of information. We will elaborate on them, but first, get a cup of coffee–it’s a long story.
Continue reading

Four air tanker companies protest Neptune’s new contract

BAe-146 drops on Devore Fire
Neptune’s BAe-146 drops on the Devore Fire, November 5, 2012. Photo by Rick McClure.

Four air tanker companies are protesting the non-competitive contract that the U.S. Forest Service gave to Neptune Aviation for two BAe-146 air tankers on December 12. As we reported that day, the contract, with a potential value of at least $141 million over four to nine years, justified the refusal to allow competition because of a necessity to “keep vital facilities or suppliers in business or make them available in the event of a national emergency, or prevent the loss of a supplier’s ability and employees’ skills”.

The Missoulian reported the information late on Tuesday. Below is an excerpt from their article:

Four aerial firefighting companies have protested the U.S. Forest Service’s decision to award two next-generation air tanker contracts to Missoula-based Neptune Aviation.

Neptune received the $8.7 million annual contract for two BAe-146 jet fire bombers on Dec. 13. The challengers, AeroAir LLC, Coulson Aviation USA, Minden Air Corp. and 10 Tanker Air Carrier LLC, each filed a protest on Dec. 23 with the Government Accountability Office.

GAO attorney Gary Allen said he could not discuss the protest claims Tuesday, because they contained “protected information” that couldn’t be disclosed until after a decision was rendered. That decision is due by March 28, but Allen said he expected a resolution would be reached before then.

An earlier version of the Missoulian article incorrectly reported that we had written at Fire Aviation that the Coulson gravity-assisted RADS retardant tank was going to be installed in the seven C-130H aircraft being transferred from the Coast Guard to the U.S. Forest Service, to convert them into air tankers. We had only said that “It would not surprise us if the U.S. Air Force will be calling [Coulson] for a quote” for the tank system. We thank reporter Rob Chaney for making the correction.

 

Thanks and a hat tip go out to Scott and Dick

10 Tanker Air Carrier moves to Albuquerque, begins converting a third DC-10

Tanker 910 Rapid City
Tanker 910 landing at Rapid City, April 23, 2013. Photo by Bill Gabbert.

10 Tanker Air Carrier, the company that operates the two DC-10 air tankers, has moved their corporate headquarters from Victorville, California to the airport at Albuquerque, New Mexico.

Rick Hatton, the CEO of the company, said yesterday about the relocation that occurred in September:

We surveyed a number of sites in the Rocky Mountain West, wanting to have more of a national presence versus being perceived as a “California Only” or Region 5 resource. Albuquerque topped the list due to a combination of off-season weather, business environment, and airport facilities.

The company moved into on-airport space with additional nearby offices and a warehouse. One of the facilities is a 7,600-square-foot building previously owned by Eclipse Aviation Corp, who’s business plan was to produce and sell small jets for $1 million each, a concept that failed.

In May Mr. Hatton announced that they were moving to Casper, Wyoming but by July cancelled those plans.

10 Tanker has evaluated airports that could serve as air tanker bases for their DC-10s and identified 30 that could handle the jumbo jets either with the existing infrastructure or with the addition of a temporary mobile retardant base.

DC-10 potential reload bases
DC-10 actual and potential retardant reload bases, as determined by 10 Tanker Air Carrier. The red circles represent permanent air tanker bases at which they could reload. The blue circles are airports at which they could reload from a mobile retardant base. (click to enlarge)

Mr. Hatton said their two DC-10s, Tankers 910 and 911, so far in 2013 have delivered 4.4 million gallons of retardant on 386 flights.

They have started converting a third DC-10, speculating that it will be used in 2014.

 

Thanks go out to Jared.